SHIMLA — SJVN Limited Director (Projects) Rajesh Kumar Chandel conducted an extensive field inspection of key hydropower assets in Himachal Pradesh to evaluate ongoing construction milestones and operational standards.
The executive review covered civil construction, safety protocols, and execution timelines at the 210 MW Luhri Hydro Electric Project (Stage-I), alongside operational efficiency and maintenance practices at the 412 MW Rampur Hydro Power Station.
Hydropower Infrastructure & Operational Matrix
-
Executive Inspector: Rajesh Kumar Chandel, Director (Projects), SJVN Limited.
-
Review Date: September 8, 2026.
-
Geographic Focus: Himachal Pradesh.
-
Under-Construction Asset (210 MW Luhri HEP-I):
-
Focus Areas: Progress of civil construction, resolution of site-level issues, contractor alignment, and future workflow timelines.
-
Strategic Directive: Prioritize inter-stakeholder coordination to ensure project completion within the stipulated timeline without compromising quality or safety metrics.
-
-
Operational Asset (412 MW Rampur HPS):
-
Focus Areas: Powerhouse output metrics, plant maintenance routines, technical readiness, and safety protocols.
-
Strategic Directive: Maintain grid reliability, operational safety, and optimal power generation efficiency.
-
-
Sustainability Focus: Planted a sapling on the project premises, reinforcing SJVN’s commitment to environmental stewardship across power asset development.